Maintenance: the maintenance RAG report

Who it's for
Maintenance managerArea support managerNursery manager
Where to find it
Maintenance › RAG Report
Time
5 minutes
You need
Maintenance access: Read-only or above

Purpose​

The report is a one-page summary of maintenance for the nurseries you can see: how many jobs are red, amber and green, what has been done and spent, what's still open, and roughly how long it will take to clear. Use it for monthly reviews, budget conversations and board reports.

Before you start​

  • You have maintenance access. The report covers the nurseries you can see: everything for group-wide users, your own nursery otherwise.
  • The figures are only as good as the jobs: keep statuses, estimates and actual costs up to date.

Open and read the report​

  1. In the menu, select Maintenance, then RAG Report at the top right. The report is worked out when you open it, and says when 1 and which nurseries it covers.
  2. RAG Status Snapshot 2: how many open jobs are Red (overdue or critical priority), Amber (at risk or approaching due) and Green (on track), as numbers and a bar.
  3. Work Completed 3: jobs completed in the last 3, 6 and 12 months with what they cost, and the most recently completed jobs. Select one to open it.
  4. Budget & Costs: Spent in the last 3 and 12 months (the actual cost where it's recorded, otherwise the estimate), Quoted (open) from accepted quotes on open jobs, the Estimated pipeline of open jobs, and Spend by category (12 months).
  5. Open Work Pipeline: open jobs by status, and Open items per nursery with how many are red and amber.
  6. Time to Completion Estimate: the Completion rate (jobs completed per month, averaged over the last 3 months), the Open items, and Est. months to clear at that rate, with a short backlog summary.
The Maintenance Report showing the RAG Status Snapshot with 3 red, 10 amber and 5 green open jobs, and Work Completed figures for the last 3, 6 and 12 months
The top of the maintenance RAG report.

What you should see​

Each section reflects your jobs as they are when you open the report. To keep a copy, use your browser's Print and choose to save as PDF.

Common problems​

The report counts more open jobs than the board.
The report counts jobs in Quality check as open; the board's open count leaves them out.
Spend is lower than I expected.

Spend comes from jobs marked Completed, using the actual cost or the estimate. Record the Actual Cost (£) on each job when it's paid, and complete jobs when they're done.

Time to Completion Estimate says "Not enough history yet".
Beacon needs jobs completed in recent months to work out a rate. It appears once jobs start being completed.